询问电池储能报价前,RFQ 应包含哪些内容

电池储能 RFQ 应在询价前明确运行曲线、接口与验收测试,以下清单可确保不同供应商的方案具备可比性。

1044 kWh Containerised Energy Storage System (4 × 261 kWh) — AllGrand product photograph 1
A comparable battery storage RFQ specifies the duty case and interfaces so suppliers quote the same scope.

Direct answer: A battery storage RFQ should define the operating profile, the electrical and site interfaces, the performance guarantee and its test method, and the scope boundary between suppliers before a price is requested. Leading with the duty case, outage duration, ambient range, grid configuration and acceptance tests produces quotes that can be compared. A price received without these inputs is a budget number, not an engineering proposal.

Asking for a price too early is the most common procurement mistake in battery storage. When the request does not fix the load, the interfaces or the acceptance method, each supplier makes different assumptions, and the returned prices describe different systems. The result is a comparison of numbers that were never intended to be compared.

This guide lists what belongs in the request before a price is asked. It is a planning reference for an international commercial or industrial purchase; every project must still be reviewed against the local grid code and the supplier’s engineering scope.

Start with the operating profile

The supplier cannot select or size a system without knowing what it must do. Provide the measured load data as time-stamped interval data, the required critical load, the outage duration to be supported, and the daily or seasonal cycling pattern. State whether the system is for backup, peak shaving, demand-charge control, self-consumption or a combination of services.

Describe the worst case, not only the average. A facility may average 180 kW but draw 420 kW for a motor start or a production shift. The RFQ should tell the supplier the highest sustained power, the longest outage and the coldest starting temperature, because those conditions drive the design more than the annual energy total.

Define the electrical and site interfaces

Ambiguity at interfaces is where projects stall and costs appear after award. Specify the grid voltage, phase configuration, earthing arrangement, available fault level and transformer size. State whether export is permitted and whether the utility imposes limits on power injection or requires specific control behavior.

For the site, describe indoor or outdoor installation, the available footprint, access for delivery and lifting, floor loading, flood and seismic exposure, and any separation or fire-protection requirements that apply locally. Ask each supplier to mark the exact boundary where their scope ends and another supplier’s scope begins, including cables, control signals, protection settings and commissioning.

Request a performance guarantee and its test method

A useful guarantee states the power and energy the system must deliver, at what temperature, at the beginning and end of the service period, and how it will be tested. A number without these conditions is not verifiable. Request the test procedure, instrumentation, allowed uncertainty and the definition of the alternating-current measurement point.

Separate a standard or design rule from a certification. Ask for the exact standards, report references, revisions and scope that apply to the proposed configuration, and request the evidence for each. A product designed to a standard is not the same as a product certified against it, and the RFQ should ask which is which.

Fix scope, delivery and acceptance boundaries

List the deliverables the price must include: the battery and enclosures, the power conversion system, controls and energy management software, transformer and switchgear where applicable, transportation, installation, commissioning, documentation and training. If any of these sit outside the quote, require the supplier to say so explicitly rather than assuming the boundary.

Define acceptance in advance. A factory acceptance test plan, a site test plan and the witness points belong in the RFQ so both sides know when the system is accepted. Include the documents required at handover, such as the single-line diagram, protection settings, test reports, operating manuals and the spare-parts list.

Where responsibilities are shared between suppliers, assign each interface explicitly in the request so there is no gap between the battery, the power conversion system and the switchgear.

A review checklist before the request is sent

Use the checklist below as a final pass. A missing item rarely kills the project, but it usually returns later as a price change or a schedule delay.

Battery storage RFQ completeness checklist
Area What the RFQ must state Why it matters
Duty case Interval load data, critical load, autonomy, cycling Determines power, energy and service
Grid interface Voltage, phases, fault level, export limits Sets protection and conversion design
Site constraints Footprint, access, environment, separation Affects enclosure and layout
Performance Guarantee values, conditions and test method Makes the offer verifiable
Scope boundary Deliverables, interfaces and exclusions Prevents post-award surprises
Acceptance Factory and site tests with witness points Defines completion and handover

Send the same checklist to every supplier and require the same format of response. Consistency in the request is what makes the responses comparable, far more than any single technical feature.

Compare like with like after the responses arrive

When the quotes return, normalize them onto one table. Check that each supplier quoted the same autonomy, the same end-of-life capacity, the same scope boundary and the same acceptance tests. Where they differ, ask for the assumption in writing. A lower price that assumes a narrower scope is not a saving; it is a smaller system.

For a reference of the product range a request can describe, review the AllGrand product family and the 1044 kWh containerized energy storage system. Buyers who need custom configuration can include the OEM and ODM support path in the request where it applies. Every configuration must still be confirmed by engineering review for the site.

Frequently asked questions

Why should I not ask for a price first?

Because each supplier will assume a different duty case, scope and test method, and the prices will describe different systems. Fixing the operating profile, interfaces and acceptance tests first is what makes the returned numbers comparable.

What is the single most useful document to attach?

The time-stamped interval load data with the critical-load list. It lets the supplier see the peak power, the energy requirement and the cycling pattern, which together drive the sizing more than any single capacity figure.

How do I compare a cheaper quote with a more expensive one?

Normalize both onto the same autonomy, end-of-life capacity, scope boundary and acceptance tests. Where the assumptions differ, ask for them in writing; a lower price that assumes less scope is not an equivalent offer.

Is a design-to-standard the same as certification?

No. A product designed to a standard is not automatically certified against it. The RFQ should ask for the exact standards, report references, revisions and scope that apply to the proposed configuration and the evidence for each.

What to send for a technical review

Send the site location, interval load data, critical-load list, outage duration, grid configuration, ambient-temperature range and available footprint to the AllGrand engineering team. The team can review the scope and assumptions before the request is finalized.

Read more energy storage engineering guides from AllGrand. AllGrand Group has manufactured batteries since 1987 and supplies energy storage systems, lead-acid batteries and battery cells to customers in more than 100 countries. Project specifications and certification scope must be confirmed for the actual site and configuration.

Sources and further reading

These sources were used to verify general energy-storage procurement concepts. The RFQ structure, checklist and comparison guidance are original AllGrand editorial work.

Continue your technical review

Related engineering guides

通信备用电池选型:备电时长与使用寿命 通信备用电池不能只按安时数选型,应综合所需备电时长、站点温度、放电倍率和维护可达性。 Read the guide → 电池削峰填谷容量设计:让储能匹配区间负荷数据 削峰容量设计应从区间负荷数据与目标需量开始,让储能功率和持续时间匹配需求缺口,再预留效率与预测余量。 Read the guide → 铅酸与 LFP 商业备用电池:选型决策矩阵 铅酸与 LFP 电池适用于不同的备用工况。可用该决策矩阵比较循环能力、温度、占地、监控与全生命周期成本。 Read the guide →

Related product routes

Compare the battery options for this application

铅改锂电池 铅酸电池的即插式 12.8 V LFP 替代品,具有蓝牙监控功能 - 适用于房车、低速车辆、小型 UPS 和船舶系统。 Review technical data → 备用电源电池,6-GFM 系列(12 V) 适用于 UPS、数据中心、信号与应急照明的阀控式胶体电池,12 V 系列覆盖 24–250 Ah。 Review technical data → 1044 kWh 集装箱式储能系统(4 × 261 kWh) 四台 261 kWh 液冷储能柜组成户外集装箱式系统,适用于公用事业及基础设施级储能。 Review technical data →

Not sure which route fits? Send the application, voltage, load profile and target runtime and our engineers will narrow it down. Request a selection review

Project engineering

Need help applying this guide to a real project?

Send the application, required capacity or runtime, site country and target delivery date. The AllGrand engineering team will review the requirement and reply within one business day.