Battery Energy Storage Factory Acceptance Test: A Buyer Checklist

Agree the FAT plan, witness points and pass criteria before production so factory testing proves the system the buyer actually ordered.

1044 kWh Containerised Energy Storage System (4 × 261 kWh) — AllGrand product photograph 1
A factory acceptance test proves the system against a written plan before it ships, while corrections are still cheap.

Direct answer: A battery energy storage factory acceptance test proves the system against a written plan before it leaves the factory. Agree the test scope, the witness points, the pass criteria and the documentation before production starts, then witness the inspection, protection and performance checks that matter. Anything found at the factory is cheaper to fix than the same defect found on site after shipping.

The factory acceptance test, or FAT, is the buyer’s strongest quality gate before equipment ships. It confirms that the system was assembled to the approved design and that it performs as specified under controlled conditions.

This guide gives a procurement checklist for planning and witnessing a battery energy storage FAT. It is a planning reference; the final test plan and pass criteria must be agreed with the supplier and the project engineer.

Agree the test plan before production

The FAT should be defined in the contract or quality plan, not invented on the day of the test. The plan lists each test, its procedure, the equipment used, the pass criterion and whether the buyer witnesses it in person or by document.

Agree which tests are hold points, where production cannot proceed until the buyer or an agreed inspector signs off, and which tests are witnessed later by record. Hold points protect the buyer because they stop the line at a decision point rather than after everything is finished.

Confirm the acceptance reference for each test, whether it is a standard, a specification clause or a drawing. A test without an agreed pass criterion is an exercise, not an acceptance gate.

Witness inspection and documentation

Inspection confirms the physical system matches the order. Check the nameplate and model numbers, the enclosure, the module serial numbers and the configuration against the approved documents, and record the results against the as-built drawings.

Review the documentation trail at the same time: the bills of materials, the component test records, the calibration certificates for the test instruments and any non-conformance reports that were closed during assembly. A system that passes its final test still needs the paperwork to prove how it was built.

Ask about any deviations from the approved design. A substitution or a repair that was closed without the buyer’s knowledge can change performance, so deviations should be listed and approved in the FAT record.

Witness functional and protection tests

Functional tests confirm the system operates as designed. Witness the start-up and shutdown sequence, the contactor and pre-charge operation, the cooling system response, the communication links to the battery management system and the power conversion system, and the alarm and safety interlocks.

Protection tests are the heart of the FAT for energy storage. Confirm that overvoltage, undervoltage, overcurrent and temperature protections trip at the agreed thresholds and that the trip is reported correctly. These tests prove the safety functions, so they deserve close attention.

Where a test uses injected signals or simulated faults, check that the test method is stated and that the results match the design values. A protection test that trips outside the agreed setting is a defect, even if the system otherwise appears healthy.

Check capacity and performance within FAT scope

A full capacity or cycle test is not always practical at the factory, so be clear about what the FAT covers. Where a capacity or charge and discharge check is in scope, agree the conditions: the temperature, the rate, the end voltage and the reference state of charge.

Compare the measured performance with the specification at the stated conditions, and note any differences from the factory reference environment. A result measured at a different temperature or rate cannot simply be compared with the nameplate figure.

If a full performance test is deferred to site commissioning, write that deferral and its acceptance method into the record. The FAT should still prove every function that can reasonably be tested before shipping.

Close the punch list and sign off

Every finding from the FAT goes onto a punch list with a category, an owner and a due date. Critical findings block shipment until they are corrected and re-tested, while minor items can be tracked to closure with a documented follow-up.

Re-test anything that was corrected, rather than accepting the original result. A fix changes the system, so the affected test should be repeated and recorded, not assumed to still pass.

Sign the FAT report only when the critical items are closed and the test record is complete. The signed report is the evidence that the system left the factory in the agreed condition, and it is the baseline for commissioning and any later warranty discussion.

Battery energy storage FAT witness checklist
Area What to witness Pass evidence
Inspection Nameplate, models, serial numbers, configuration As-built check record
Documentation Test records, calibrations, non-conformances Complete document pack
Functional Start-up, cooling, communications, interlocks Signed test sheets
Protection Voltage, current and temperature trips Trip settings and results
Punch list Findings, owners and due dates Closed and re-tested

Use this checklist when planning the FAT and again when reviewing the report. A row without a pass record is a gap to close before the system ships.

Plan the witness logistics in advance

A FAT is only as good as the people who can see it. Decide in advance who attends, whether in person or by live video, what authority they have to accept or reject a test, and how results are recorded and distributed. Remote witnessing needs the same access to the test equipment and the same decision rights as an on-site visit.

Schedule enough time for the hold points and the re-tests, because a test that is rushed to meet a shipping date tends to lose its value as a gate. Agree the report format before the test so the sign-off happens against a known record.

Frequently asked questions

What is the difference between a FAT and a SAT?

A factory acceptance test runs before shipment under factory conditions, while a site acceptance test runs after installation. The FAT catches build defects early; the SAT confirms the system works in its installed environment.

What is a witness point at a FAT?

It is a test the buyer or an agreed inspector observes before production can pass it. Hold points are witness points that stop the line until the buyer signs off.

Do I need a full capacity test at the factory?

Not always. Where a full capacity test is impractical, agree the conditions for any performance check or defer it to site commissioning with a written acceptance method. Every function that can be tested should still be tested.

What happens to FAT findings after the test?

They go onto a punch list with a category, owner and due date. Critical findings block shipment until corrected and re-tested, while minor items are tracked to documented closure.

What to send for a technical review

Share the proposed FAT plan, the specification clauses and the witness requirements with the AllGrand engineering team. The team can review the test scope for the 1044 kWh containerized energy storage system. Read more BESS procurement guides. AllGrand Group has manufactured batteries since 1987 and supplies energy storage systems to customers in more than 100 countries. The test plan must be confirmed by engineering review.

Sources and further reading

These sources were used to verify general testing, assurance and energy storage concepts. The FAT checklist and witness method are original AllGrand editorial work.

Continue your technical review

Related engineering guides

Commercial Battery Storage Cost: What Drives the Budget? Commercial battery storage cost is driven by the whole system, not the battery alone. Compare scope, usable energy, power and… Read the guide → Battery Storage Fire Safety: What Evidence Buyers Should Verify Verify the listing scope, fire test report, detection design and installation review before accepting a battery storage fire safety package. Read the guide → Commercial Battery Energy Storage System Supplier: 12 Checks A 12-question due-diligence checklist for comparing commercial BESS suppliers, scope, interfaces, safety evidence, guarantees and service terms. Read the guide →

Related product routes

Compare the battery options for this application

Standby Power Battery, 6-GFM Series (12 V) Valve-regulated gel batteries for UPS, data centres, signalling and emergency lighting, 24 - 250 Ah at 12 V. Review technical data → Lead-to-Lithium Battery A drop-in 12.8 V LFP replacement for lead-acid batteries, with Bluetooth monitoring — for RVs, low-speed vehicles, small UPS and marine systems. Review technical data → 1044 kWh Containerised Energy Storage System (4 × 261 kWh) Four 261 kWh liquid-cooled cabinets in a containerised outdoor system, for utility and infrastructure scale storage. Review technical data →

Not sure which route fits? Send the application, voltage, load profile and target runtime and our engineers will narrow it down. Request a selection review

Project engineering

Need help applying this guide to a real project?

Send the application, required capacity or runtime, site country and target delivery date. The AllGrand engineering team will review the requirement and reply within one business day.